PROJECT:  Consultant for design verifications in PATHE Management Consultant

CLIENT: J/V MOTT - BERGER (since 2002  Louis Berger group inc.).
ASSOCIATED OFFICES: EYDE - PATHE                                         

BRIEF DESCRIPTION:
 
Design verification of a significant number of final designs of bridges and pile retaining walls, certified as a Class A inspector engineer. Indicative projects:
  • Final design of the, incremental launched, viaduct at Ch 263+673 with spans  31.5+58.5+53.0 m
  • Final design of river Xirias bridge at Ch 285+748  with spans 25.2+26.0+25.2 m
  • Final design bridges of interchange Skotina
  • Final design of the bridge C4 (ancient wall Alu) at Ch 279+965
  • Final design of bridge at Ch 19+244
  • Final design of the bridge OP KO7 (road to Dion) at Ch 14+847
  • Final design of the bridge of interchange Ephesus-Dion
  • Final design of bridge at Ch 12+733
  • Final design of the bridge at T4 Ch 4+962
  • Final design of the bridge of interchange Evaggelismos at Ch 7+713
  • Final design of the bridge at Ch 2+518 span 31.7m
  • Final design of the bridge in Aerino access road (from km Ch 0+025 to Ch 0+424) for the protection of archaeological sites
  • Modification of the final design of the bridge river Ziliana at Ch 1+179
  • Final design of UP bridge Kileler-Perivoli at Ch 7+568
  • Final design of UP bridge at Ch 285+532
  • Final design of UP bridge at Ch 286+101
  • Final design of UP bridge at Ch 272+022
  • Final design of UP bridge - K11 at Ch 280+812
  • Final studies of pile retaining walls in the section " Pelasgia Tolls - intersection Ag. Theodoroi"
  • Specifications for the design of Section Almyros bypass
  • Preliminary designs of Reinforced Earth walls in Section Agios Konstantinos - Kammena Vourla
  • Final design of the bridges of interchange Korinos
  • Final design of retaining walls in Section Kakia Skala
  • Final design of steel frames of motorway electronic signs at section Kakia Skala
 
The project has been completed and is in operation.
 
Design years: 1997-2005
Design standards: DIN, Greek Earthquake Design Standard (EAK)

     See